Project Information

Client / Contractor : Umm AL-Qura / Nesma & Partners Contracting Co. Ltd

Description : Construct of car park3 – (segment 11,12, Zone 8-(5 floors with (16,000 m110,000-2 m3) and Construct of utility galleries Zone 6 tunnel – 4 kl length with 45000 m3 and 2 entrance Mosque station 5000 m3.

Work Duration : 44 months

Project Value : (84,000,000) SAR

MASAR Project

MASAR Project was an extensive and multifaceted construction effort that involved several key components, including the construction of Car Park 3 (Segment 11, 12, Zone 8) with five floors, totaling 16,000 m² and 110,000 m³, and the construction of utility galleries within Zone 6 tunnel—a 4-kilometer-long tunnel requiring 45,000 m³ of material. Additionally, the project included the construction of two entrances for the Mosque station, utilizing 5,000 m³. This complex project was successfully executed over 44 months, showcasing precision engineering and robust project management.

×